GUGLER Water Turbines is proud to announce the successful restoration and enhancement of the Moco Moco Hydropower Plant in Guyana. Originally commissioned in 1999, the plant was damaged by a landslide in 2003 and had been out of service since then. Following its rehabilitation, the plant is now fully operational, with its capacity increased from 0,5 MW to 0,7 MW to meet the growing energy needs of the region.

The Moco Moco is located on the Moco Moco Creek, part of the Amazon River system, features a high net head of 206,9 meters and a flow rate of 0,22 m³/s. The plant operates with two horizontal Pelton turbines, each designed for high efficiency in challenging conditions. With turbines running at 1 200 rpm, the plant now provides reliable, renewable energy to the Lethem area.

Moco Moco, Guyana, 2024

Scope of Supply: Pelton Turbines (2x 0,22 m³/s), Generator, Flywheel, HPU, Inlet Valve, Control & Protection Equipment, Switchgear, Auxiliary Supply System

Number of Units
2
Total Output (kW)
787
Head of water (m)
206,9
Flow (m3/s)
0,2
Runner Diameter (mm)
488

About GUGLER Water Turbines GmbH:

GUGLER Water Turbines GmbH is a leading supplier of – state of the art – turbine technology, supplying all types of Francis, Kaplan and Pelton turbines up to 40 MW per unit and related electro-mechanical equipment for small and medium sized hydro power plants (water to wire).

GUGLER Water Turbines GmbH supplies also special turbines, such as micro turbines, container turbines, siphon turbines, gates turbines, turbines for drinking water , waste water and salt water systems on a global basis.