Successful projects in Colombia and Vietnam

1) Successful commissioning of two hydropower plants in Vietnam

Earlier this year GUGLER Water Turbines GmbH successfully commissioned Nam Be 2 and Nam Cuoi hydropower plants in Vietnam.

Nam Be 2 hydropower plant consists of two (2) Francis turbines designed for a net head of 158 m and nominal flow of 4 m3/s each with an installed capacity of 11.5 MW.

Nam Cuoi hydropower plant consists of two (2) Francis turbines designed for a net head of 46 m and nominal flow of 15,18 m3/s each with an total installed capacity of 12.2 MW.

2) Successful commissioning in Colombia:

In 2nd quarter of 2024, GUGLER Water Turbines GmbH successfully commissioned the two (2) Francis turbines with all the associated electromechanical equipment for the new Tarazá II hydropower plant in Colombia. The new power plant with an installed capacity of almost 10 MW located in the Antioquia province of Colombia.

The two horizontal Francis turbines were designed for a net head of 72,15 m and nominal flows of 10 m3/s and 5 m³/s respectively to generate 6.5 MW and 3.3 MW respectively.

(July 2024)

About GUGLER Water Turbines GmbH:

GUGLER Water Turbines GmbH is a leading supplier of – state of the art – turbine technology, supplying all types of Francis, Kaplan and Pelton turbines up to 40 MW per unit and related electro-mechanical equipment for small and medium sized hydro power plants (water to wire).

GUGLER Water Turbines GmbH supplies also special turbines, such as micro turbines, container turbines, siphon turbines, gates turbines, turbines for drinking water , waste water and salt water systems on a global basis.

Consent Management Platform by Real Cookie Banner