Philippines – Successful commissioning of 20 MW Bineng HPP

In June 2019 GUGLER Water Turbines has successfully commissioned two (2) vertical Pelton turbines with 6 nozzles with a power output of 10 MW each for Hedcor Inc., a company of renowned Aboitiz group.

The Pelton turbines have been designed for a net head of 439 m and a discharge of 2.52 m³/s per unit.The new hydropower plant Bineng is located near the city of Baguio City, Northern Luzon.

(July 2019)

Bineng, Philipines, 2019

Volume de livraison: Pelton Turbine, Spherical Valve, HPU, Generator, Electrical switchgears, Control and Protection System

Nombre d'unités
2
Rendement total (kW)
20 654
Hauteur de chute (m)
460.78
Débit (m3/s)
2.52
Diamètre de la roue (mm)
938

Bineng, Philipines, 2019

Volume de livraison: Pelton Turbine, Spherical Valve, HPU, Generator, Electrical switchgears, Control and Protection System

Nombre d'unités
2
Rendement total (kW)
20 654
Hauteur de chute (m)
460.78
Débit (m3/s)
2.52
Diamètre de la roue (mm)
938

About GUGLER Water Turbines GmbH:

GUGLER Water Turbines GmbH is a leading supplier of – state of the art – turbine technology, supplying all types of Francis, Kaplan and Pelton turbines up to 40 MW per unit and related electro-mechanical equipment for small and medium sized hydro power plants (water to wire).

GUGLER Water Turbines GmbH supplies also special turbines,such as micro turbines, container turbines, siphon turbines, gates turbines, turbines for drinking water pipelines on a global basis.

Plateforme de Gestion des Consentements par Real Cookie Banner